• Contract Date: 2021
  • client: Rail Vikas Nigam Limited
  • Name of Work:
    Detailed Design And Project Management Consultancy For Construction Of Tunnels From Chainage Km 20+890 To Km 32+00 And Works Related To Minor Bridges And Formation On Approaches Of Such Tunnels In Connection With New Single Line Broad Gauge Rail Link Between Bhanupali- Bilaspur-Beri In The State Of Punjab And Himachal Pradesh, India

RVNL Bhanupalı-Bılaspur-Berı T8-T10

This project includes Detailed Design and Project Management Consultancy services during preconstruction and construction stage of various works in connection with construction of Tunnel no. 8 to Tunnel no. 10 and will broadly involve related railway formation works, drainage system, stability of slope on approaches of these Tunnels including minor bridges on such approaches between km 20+890 to km
32+100.

 